Project Overview
Water, sanitary sewer, drainage, and paving improvements for Sterling Traditions Section 2, including utility installation, storm sewer, concrete paving, trench safety, dewatering, SWPPP controls, and site restoration.
Scope of Work
- Water services, valves, fittings, and flushing assemblies
- Sanitary sewer installation
- Sanitary sewer manholes and service leads
- 10-inch sanitary force main
- RCP storm sewer installation
- Storm sewer manholes and inlets
- Concrete paving and roadway appurtenances
- Trench safety and dewatering
- SWPPP, erosion control, and site restoration
- 8-inch and 12-inch waterline installation
“Self-performed civil from clearing through final paving — one schedule, one foreman, one number.”
Project Timeline
- ● Active · Q2 2026Mobilization & Site Preparation
Mobilize crews and equipment, establish access, install SWPPP controls, and begin layout for utility and paving construction.
- ● Active · Q2 2026Water & Sanitary Sewer Installation
Install waterline, valves, water services, sanitary sewer pipe, service leads, force main, and sanitary manholes.
- Upcoming · Q2–Q3 2026Drainage & Storm Sewer Improvements
Install RCP storm sewer, storm manholes, inlets, trench safety, dewatering, and drainage-related structures.
- Upcoming · Q3 2026Paving, Restoration & Closeout
Complete concrete paving, driveways, curbs, pavement markings, testing, erosion control cleanup, site restoration, and final closeout.