MOVING DIRT · BUILDING ROADS · DEVELOPING COMMUNITIESBUILD YOUR CAREER WITH A FAMILY-OWNED HOUSTON CONTRACTOR832-409-5740WE ARE HIRING: Fuel Lube Truck Drivers, PM Mechanics, Foremen, Superintendents, CDL Water Truck Drivers, Estimators, and Operators.MOVING DIRT · BUILDING ROADS · DEVELOPING COMMUNITIESBUILD YOUR CAREER WITH A FAMILY-OWNED HOUSTON CONTRACTOR832-409-5740WE ARE HIRING: Fuel Lube Truck Drivers, PM Mechanics, Foremen, Superintendents, CDL Water Truck Drivers, Estimators, and Operators.
NorthTex Construction
Home/Projects/McCrary Road
Delivered

McCrary Road

Northtex Construction is performing a roadway reconstruction and widening

Budget
$12.2M
Timeline
18 months
Team
25–40 personnel
Scope
Roadway widening with concrete paving, drainage, sidewalks, traffic signals, and site restoration.
Status
Complete
Client
Fort Bend County, Texas

Project Overview

Northtex Construction is performing a roadway reconstruction and widening project for McCrary Road from FM 359 to Old McCrary as part of the Fort Bend County Mobility Bond Program. The project includes roadway widening, paving, excavation, drainage, storm sewer, box culverts, detention pond items, outfall channel work, traffic signal work, sidewalks, curbs, driveways, and related site improvements.

Client
Fort Bend County, Texas
Earthwork
Roadway excavation, borrow, clearing & grubbing, drainage/outfall excavation
Schedule
548 calendar days
Delivered
Q3 2025

Scope of Work

  • Roadway reconstruction and widening
  • Site preparation and excavation
  • Reinforced concrete pavement
  • Storm sewer and drainage structures
  • Box culverts and outfall channel improvements
  • Concrete curbs, sidewalks, driveways, and ADA ramps
  • Detention pond improvements
  • Traffic signal work
  • SWPPP, erosion control, and site restoration
“Self-performed civil from clearing through final paving — one schedule, one foreman, one number.”

Project Timeline

  1. ✓ Complete · Q2 2024
    Mobilization & Site Preparation

    Mobilize crews and equipment, install traffic controls, coordinate utilities, and prepare the roadway work zone.

  2. ✓ Complete · Q2–Q4 2024
    Earthwork, Drainage & Utility Coordination

    Complete roadway excavation, storm sewer installation, box culvert work, outfall channel improvements, and utility coordination.

  3. ✓ Complete · Q1–Q2 2025
    Concrete Paving & Roadway Improvements

    Install reinforced concrete pavement, curbs, sidewalks, driveways, ADA ramps, and related roadway improvements.

  4. ✓ Complete · Q3 2025
    Signals, Restoration & Closeout

    Complete traffic signal work, detention improvements, final grading, erosion control cleanup, striping, inspections, and project closeout.

/05Outcomes

What we delivered.

Roadway
Property Type
Reconstruction and widening
Drainage
Drainage System
Storm sewer, detention, and outfall improvements
Public
Infrastructure
Fort Bend County roadway project
Q3 2025
Delivery
Completed