Project Overview
Northtex Construction is performing a roadway reconstruction and widening project for McCrary Road from FM 359 to Old McCrary as part of the Fort Bend County Mobility Bond Program. The project includes roadway widening, paving, excavation, drainage, storm sewer, box culverts, detention pond items, outfall channel work, traffic signal work, sidewalks, curbs, driveways, and related site improvements.
Scope of Work
- Roadway reconstruction and widening
- Site preparation and excavation
- Reinforced concrete pavement
- Storm sewer and drainage structures
- Box culverts and outfall channel improvements
- Concrete curbs, sidewalks, driveways, and ADA ramps
- Detention pond improvements
- Traffic signal work
- SWPPP, erosion control, and site restoration
“Self-performed civil from clearing through final paving — one schedule, one foreman, one number.”
Project Timeline
- ✓ Complete · Q2 2024Mobilization & Site Preparation
Mobilize crews and equipment, install traffic controls, coordinate utilities, and prepare the roadway work zone.
- ✓ Complete · Q2–Q4 2024Earthwork, Drainage & Utility Coordination
Complete roadway excavation, storm sewer installation, box culvert work, outfall channel improvements, and utility coordination.
- ✓ Complete · Q1–Q2 2025Concrete Paving & Roadway Improvements
Install reinforced concrete pavement, curbs, sidewalks, driveways, ADA ramps, and related roadway improvements.
- ✓ Complete · Q3 2025Signals, Restoration & Closeout
Complete traffic signal work, detention improvements, final grading, erosion control cleanup, striping, inspections, and project closeout.