Project Overview
Sanitary sewer utility repair project including removal and replacement of an 8-inch sanitary line, 12-inch casing/line adjustment, sanitary manhole replacement, vacuum-assisted dewatering wells, trench safety, temporary construction access, sidewalk replacement, and fence restoration.
Scope of Work
- Sanitary sewer line replacement
- Sanitary manhole removal and replacement
- 12-inch casing/line adjustment to grade
- Vacuum-assisted dewatering wells
- Trench safety and excavation support
- Temporary construction access
- Sidewalk and fence restoration
- Mobilization and site restoration
“Self-performed civil from clearing through final paving — one schedule, one foreman, one number.”
Project Timeline
- ● Active · May 2026Mobilization & Site Access
Set up temporary construction access, safety controls, and prepare the work area for sanitary sewer repair.
- ● Active · May 2026Dewatering & Trench Safety
Install vacuum-assisted dewatering wells and set trench protection, including trench boxes, plates, and sheet piles.
- ● Active · May–June 2026Sanitary Line & Manhole Replacement
Remove and replace the 8-inch sanitary line, adjust the 12-inch casing/line to grade, and replace Sanitary Manhole No. 1.
- ● Active · June 2026Restoration & Final Cleanup
Replace sidewalk and fence, remove temporary access, restore disturbed areas, and complete final cleanup.