Project Overview
Drainage, detention, and mass grading improvements for Midline Phase 2, including excavation, embankment, storm sewer, box culverts, swales, dewatering, seeding, and site restoration.
Scope of Work
- Mass grading and excavation
- Detention pond construction
- Embankment and fill placement
- Storm sewer installation
- Reinforced concrete box culverts
- Interceptor swales and drainage grading
- Dewatering and surface water control
- Removal of existing utilities and structures
- Seeding, erosion control, and site restoration
- As-built survey and project closeout
“Self-performed civil from clearing through final paving — one schedule, one foreman, one number.”
Project Timeline
- ✓ Complete · Q1 2026Mobilization & Site Preparation
Mobilize crews and equipment, establish access, install SWPPP controls, and prepare the site for mass grading and drainage construction.
- ● Active · Q1–Q2 2026Mass Grading & Earthwork
Complete excavation, embankment, fill placement, removal of existing items, and rough grading for Midline Phase 2.
- ● Active · Q2–Q3 2026Detention & Drainage Improvements
Construct detention pond areas, install storm sewer, drainage structures, interceptor swales, and reinforced concrete box culverts.
- Upcoming · Q3–Q4 2026Final Grading & Closeout
Complete final grading, seeding, erosion control cleanup, as-built survey, site restoration, and project closeout.