Project Overview
Construction work for the Trinity Landing Development, including mass grading, detention pond work, drainage structures, abandoned pipeline removal, and final site cleanup. The contract says the major work includes excavation and embankment for detention ponds and Trinity Landing sections, construction of concrete drainage structures, removal of abandoned pipeline, and cleanup upon completion.
Scope of Work
- Mass grading and site preparation
- Detention pond excavation
- Embankment and fill placement
- Drainage improvements
- Concrete drainage structures
- Abandoned pipeline removal
- Final grading and cleanup
- Site stabilization
“Self-performed civil from clearing through final paving — one schedule, one foreman, one number.”
Project Timeline
- ✓ Complete · Q4 2025Mobilization & Site Prep
Mobilize equipment, establish access, prepare the work area, and begin clearing/site preparation.
- ● Active · Q4 2025–Q1 2026Mass Grading & Earthwork
Perform mass grading, excavation, embankment, and fill placement for the Trinity Landing development areas.
- ● Active · Q1–Q2 2026Detention & Drainage Improvements
Construct detention pond areas, install drainage improvements, and complete concrete drainage structures.
- Upcoming · Q2–Q3 2026Final Grading & Site Cleanup
Complete final grading, remove abandoned pipeline items, stabilize disturbed areas, and perform final cleanup.