Project Overview
Detention, utilities, storm drainage, paving, and site restoration for a residential subdivision.
Scope of Work
- Clearing, grubbing, and site preparation
- Phase Two detention basin construction
- Amenity lake excavation and dewatering
- Storm sewer installation
- Storm junction boxes, inlets, manholes, and swales
- Water distribution system installation
- Wastewater collection system installation
- Trench safety and dewatering
- Concrete paving, curbs, sidewalks, and ramps
- SWPPP, erosion control, turf establishment, and site restoration
“Self-performed civil from clearing through final paving — one schedule, one foreman, one number.”
Project Timeline
- ✓ Complete · Q1 2026Mobilization & Site Preparation
Mobilize crews and equipment, begin clearing and grubbing, prepare access, install SWPPP controls, and start site layout.
- ✓ Complete · Q1–Q2 2026Detention & Earthwork
Construct Phase Two detention facilities, complete basin excavation, amenity lake excavation, dewatering, swales, and major earthwork.
- ● Active · Q2–Q3 2026Water, Wastewater & Storm Sewer
Install water distribution, wastewater collection, storm sewer, inlets, manholes, junction boxes, trench safety, and dewatering systems.
- Upcoming · Q3–Q4 2026Paving, Restoration & Closeout
Complete concrete paving, curbs, sidewalks, ramps, SWPPP cleanup, turf establishment, final grading, and project closeout.