Project Overview
Water, wastewater, stormwater, paving, and grading improvements for Meridiana Section Eight-A.
Scope of Work
- Site preparation and stripping
- Water distribution system installation
- Sanitary sewer installation
- Storm sewer installation
- Storm inlets, manholes, and drainage tie-ins
- Roadway excavation and grading
- Stabilized subgrade preparation
- Reinforced concrete paving and curbs
- Wheelchair ramps, signs, traffic buttons, and pavement markings
- SWPPP compliance, construction staking, as-built survey, and final cleanup
“Self-performed civil from clearing through final paving — one schedule, one foreman, one number.”
Project Timeline
- ✓ Complete · Q2 2026Mobilization & Site Preparation
Mobilize crews and equipment, complete construction staking, prepare the site, begin stripping, grading, SWPPP setup, and traffic control.
- ✓ Complete · Q2 2026First Stage Utilities
Begin water distribution, sanitary sewer, and stormwater utility installation. The milestone schedule lists first stage utilities at 35 days from NTP.
- ● Active · Q2–Q3 2026Paving & Second Stage Utilities
Complete paving operations, second stage utilities, storm sewer structures, concrete paving, curbs, ramps, signs, and pavement markings.
- Upcoming · Q3 2026Final Restoration & Closeout
Complete final grading, SWPPP cleanup, as-built survey, record drawings, punch list items, and final acceptance.